General
Review and verify the following for
the custom schematic design:
- Reviewed above "Common checklist for all sections" section of the
user's guide
- Implementation approach of VPP supply (LDO (recommended) or Load Switch/FET
based switch (Not allowed))
- Supply within the Recommended operating conditions for the load (current)
transient during OTP eFuse programming
- Provision for isolation of VPP supply connected to processor for testing
- Control of VPP supply generation LDO output (LDO EN)
- Recommended bulk and filter capacitors to support current transient and
optimize discharge time
- Connection recommendations when external supply is used as VPP supply
- External VPP supply timing control
- External VPP supply sequencing
- Connecting the VPP supply to a continuous 1.8V supply rail is not
recommended or allowed or a supported option.
Schematic Review
Follow the list below for the custom
schematic design:
- Recommended bulk and filter
capacitors are provided (follow EVM schematic implementation).
- Processor supply rail
connected to the VPP supply (for eFuse programming) follows the processor
ROC.
- Implementation of on-board
supply or provision to connect external supply with the bulk and decoupling
capacitors added on the processor board.
- A fixed output LDO or PMIC
output (maximum current of 400mA) is recommended (use of FET based switch or
Load switch is not recommended or allowed).
- Choose on-board LDO that with
nominal voltage of 1.8V and supports a minimum current of 400mA, has good
load current transient response, and quick output discharge (active
discharge) capability. Follow the LDO specs used on the EVM schematics.
- When an adjustable LDO is
used, the recommendation is to verify the output voltage configuration,
output voltage accuracy, output voltage slew and use of output over voltage
protection (zener).
- Processor IO is used to
control the EN of the LDO and the recommended pull is provided.
- The recommendation is to
verify if EN pull holds the LDO in off-state during and after power
cycling.
- When external supply is
connected, the recommendation is to add bulk and decoupling capacitor
provision on the processor board near to the processor VPP pin and provided
a TP to connect the external supply.
- External VPP supply (when
used) follows the recommended power sequence and slew rate requirements as
per the processor-specific data sheet.
Additional
- The recommendation is to always
provide provision on the processor board to connect VPP supply (on-board or
external supply).
- The recommendation is to connect
LDO output to the processor VPP pin with a low loop inductance path to source
the high load current transients, where the supply on the VPP pin never drops
below the minimum operating voltage.
- Series resistor or jumper is
provided to isolate the processor VPP supply from the LDO output for testing the
timing or LDO output. The resistor package is expected to be rated for current
> 400mA.
- When an adjustable output LDO is
used, consider adding an external zener based over voltage protection at the LDO
output and provide provision to isolate the LDO output connected VPP supply pin
to test the LDO output.
- Due to the load current transient
requirement during eFuse programming, using load switch or FET based switch is
not recommended. A load switch or FET based switch is likely to have higher
voltage drop that is not compensated.
- In case the use case requires use
of load switch or FET based switch, the recommendation is to characterize the
board performance by measuring the voltage on the processor VPP pin during
programming and verify that VPP supply never drops below the ROC minimum value.
Several variables in the path of VPP supply can cause the supply to be out of
the ROC and are required to be characterized before implementing. Check if the
load switch or FET based switch violates the maximum VPP supply slew rate
requirement defined in the processor-specific data sheet.
- The recommendation is to leave
the processor VPP supply pin floating (Hi-Z) or connect to ground during
power-up sequences, power-down sequences, and normal device operation.