During power-down, VDD must be
supplied until after VBIAS, VRESET, and VOFFSET
are discharged to within the specified limit of ground. See the figure DMD
Power Supply Requirements.
During power-down, it is a strict requirement
that the voltage difference between VBIAS and VOFFSET must
be within the specified limit shown in the Recommended Operating
Conditions.
During power-down, there is no requirement for the relative timing of VRESET with respect to VBIAS.
Power supply slew rates during power-down are
flexible, provided that the transient voltage levels follow the requirements
specified in the Absolute Maximum Ratings, the Recommended Operating
Conditions, and in the figure DMD Power Supply Requirements.
During power-down, LVCMOS input pins must be less
than specified in Recommended Operating Conditions.
B. To prevent excess current, the supply voltage
difference |VBIAS – VOFFSET| must be less than the
specified limit in the Recommended Operating Conditions.
C. To prevent excess current, the supply difference
|VBIAS – VRESET| must be less than the specified limit
in the Recommended Operating Conditions.
D. VBIAS must power up after VOFFSET has powered up, per the Delay1 specification in Table 8-1.
E. VRESET, VOFFSET, and VBIAS ramps must start after VDD and VDDA are powered up and stable.
F. After the DMD micromirror park sequence is complete, the DLP controller software initiates a hardware power-down that activates DMD_EN_ARSTZ and disables VBIAS, VRESET, and VOFFSET.
G. Under power-loss conditions where emergency DMD micromirror park procedures are being enacted by the DLP controller hardware, DMD_EN_ARSTZ goes low.
H. VDD must remain high until after VOFFSET, VBIAS, and VRESET go low, per Delay2 specification in Table 8-1.
I. To prevent excess current, the supply voltage
delta |VDDA – VDD| must be less than the specified limit
in Recommended Operating Conditions.